History of the Saemangeum project
Published: 24 Apr. 2016, 19:46
January 1986: Beginning of the Saemangeum development project’s design stage.
November 1989: The Ministry of Food, Agriculture, Forestry and Fisheries announces the Saemangeum development project plan.
November 1991: Beginning of the seawall construction.
1995: Water pollution in Saemangeum Lake becomes controversial, leading to environmentalists demanding a half to the project.
May 1999: An expert review panel begins a review of the environmental effects of the Saemangeum project.
March-May 2003: Civic and religious organizations conduct a 65-day pilgrimage from Buan County to Seoul.
March 2006: The Supreme Court rules in favor of the government in a lawsuit filed by an environmental organization to stop the project due to environmental concerns.
April 2007: Initial development plan for the reclaimed lands is established with 72 percent of the land being designated for agricultural use.
October 2008: The plan for reclaimed land is revised to 30 percent of the land being designated for agricultural use.
January 2010: The plan for the reclaimed land is finalized.
April 2010: Seawall construction is completed.
December 2012: A special law is passed to support the project.
September 2013: Opening of the Saemangeum Development and Investment Agency.
September 2014: Revision and finalization of the Saemangeum project plan.
2020: Expected completion date for the first level of development of the reclaimed land.